New Trail Build Update

Andy and I got out last weekend and marked out the next project…”The Ravine Run” trail. The County has inspected and approved our proposed route so we have now started. Andy got out this week to do a bunch of chainsaw work. The next step is to remove all the logs and small debris along the route. If you have time and wish to help please feel free to do so. The trail heads off about 1/2 along the new Max Extension Trail. You will see the orange flags marking the general plan for the trail (this will likely change a bit as we go along). Removal of debris and small saplings is the next task to be completed then we will leaf blow, clear again and go from there. Any help will be appreciated.

Thanks and hope everyone is enjoying the trail additions!